For an optimal viewing experience, it is recommended to view this website on the latest versions of IE, Firefox, Chrome or Safari.

2022-07-25

Successful mega truss lifting of Kai Tak Sports Park

Our Kai Tak Sports Park (KTSP) project recently achieved a major milestone, when the Main Stadium retractable roof mega trusses were successfully lifted into position.
 
This involved the simultaneous lifting of the four prefabricated mega-trusses, which have a total net weight of over 6000 tons. The simultaneous lifting of trusses of this scale is unprecedented in Hong Kong. Multi-disciplinary teams undertook detailed engineering and risk analysis studies; conducted multiple simulations and virtual rehearsals of all aspects of the operation and the sequencing of the activities; and formulated comprehensive contingency plans. This was made possible by leveraging the power of Building Information Modelling (BIM) and Drone and Laser Scanning technology.
 
We thank our project team and all of our stakeholders for their steadfast commitment to achieve this milestone!


Back